UPDATES

Here's a quick update on Elevate’s projects. We've made significant progress and are excited to share where things stand. Here’s a snapshot of a few of our key initiatives:

The Commons

We are excited to announce that the Commons Clubhouse is officially open for resident use! The newly renovated space is ready to welcome you, and we encourage you to stop by and enjoy the upgraded amenities.

​

Thank you for your patience and support during the renovation process. 

Completed Work

We are pleased to report that all roofing work has been successfully completed. Furthermore, paving work at the North entrance and Heron Run is now fully finished, and all guardhouses, Resident Services, The Commons and Plaza del Lago have undergone painting to enhance their aesthetic appeal. The Commons Clubhouse renovation is now completed.

Plaza del Lago

Plaza Del Lago Kitchen is undergoing a renovation that began in late 2023 with demolition of the kitchen and bar area. There was a change in plans based on the city's direction. This change was completed and the project is expected to be finished by early 2025. 

Upcoming Projects:

The Commons Clubhouse is official open for resident use but still has some pending items that will need to be done. 

​ - The Pool Deck scope of work was removed from the Contractor as part of the renovation. This project will be done at a later date. 

​- The Tennis Courts are going to be completed by early 2025, the contractor - Welch Tennis has been successful in gaining the necessary permits to start the project. Welch Tennis will also be rebuilding the pickleball courts. 

​

Tennis and Pickleball 

We are pleased to share the latest update on the tennis courts project. We have received all the necessary permits for the new tennis courts, and the sitework and drainage are now 90% completed. We're making great progress!

​

We are preparing to partially reopen the existing courts by the end of October, allowing residents to enjoy the facilities once again. Additionally, construction for the new pickleball courts is scheduled to begin in November.

Tennis
September 2024 Presentation11_edited_edi

Water Park

Exciting news! The Waterpark is almost complete! The system is fully functional and is running at this time. Once the surface is completed and the mechanicals are fully tested, we will be able to get final permit approvals. Estimated time to completion will be November 2024. 