UPDATES
Here's a quick update on Elevate’s projects. We've made significant progress and are excited to share where things stand. Here’s a snapshot of a few of our key initiatives:
Completed Work
We are pleased to report that all roofing work has been successfully completed. Furthermore, paving work at the North entrance and Heron Run is now fully finished, and all guardhouses, Resident Services, The Commons and Plaza del Lago have undergone painting to enhance their aesthetic appeal. The Commons Clubhouse renovation is now completed.
Upcoming Projects:
The Commons Clubhouse is official open for resident use but still has some pending items that will need to be done.
​ - The Pool Deck scope of work was removed from the Contractor as part of the renovation. This project will be done at a later date.
​- The Tennis Courts are going to be completed by early 2025, the contractor - Welch Tennis has been successful in gaining the necessary permits to start the project. Welch Tennis will also be rebuilding the pickleball courts.
​
Tennis and Pickleball
We are pleased to share the latest update on the tennis courts project. We have received all the necessary permits for the new tennis courts, and the sitework and drainage are now 90% completed. We're making great progress!
​
We are preparing to partially reopen the existing courts by the end of October, allowing residents to enjoy the facilities once again. Additionally, construction for the new pickleball courts is scheduled to begin in November.
Water Park
Exciting news! The Waterpark is almost complete! The system is fully functional and is running at this time. Once the surface is completed and the mechanicals are fully tested, we will be able to get final permit approvals. Estimated time to completion will be November 2024.